Road Projects

_____________________________________________________________________________

The Village of Little Chute Department of Public Works is constantly undertaking a variety of projects ranging form road construction, water and sewer replacement and storm water management. Throughout the course of the year, road project updates will be available.

2023 Village Projects

2023 - CROSSWINDS SUBDIVISION SIDEWALK & STREET LIGHTING
(Gardenia Drive, Tulip Trail, and Golden Hill Court)

Public Hearing December 7, 2022

To view the PowerPoint presentation click here.

To view Frequently Asked Questions click here.

Construction will start next week, the week of April 3rd.  During the first week of construction the contractor anticipates setting up traffic control, staging equipment, materials and excavating for the new sidewalk.

Contract No. 2023001 - 2023 SIDEWALK CONSTRUCTION - CROSSWINDS SUBDIVISION

Project Completion Date:  October 27th, 2023 

Project Location/Description:

The project is located on Gardenia Drive, Tulip Trail, and Golden Hill Court between French Road and Cherryvale Avenue in the Crosswinds Subdivision. Project extends approximately 4,500 lineal feet and includes approximately 37,650 square feet of new concrete sidewalk to be constructed on both sides of the street. Contractor to remove and replace 183 lineal feet of concrete curbing and 54 square yards of asphalt pavement which is necessary to meet ADA requirements. Project also includes 3,020 square yards of landscape/turf restoration and miscellaneous proposed paint striping.

 Sommers Construction is the General Contractor for this project. Sommers has completed the excavation, forming, and concrete placement for the new sidewalk. Sub-contractor: Superior Sewer & Water, has also completed the landscaping/turf restoration. Residents should continue to water until vegetation is established.

.Crosswinds Subdivision is an active construction site. For your safety as well as those working in the area, please avoid using this area when possible.

Traffic Impacts: All streets will remain open to local traffic only during normal construction activities. Intermittent lane restrictions and closures will take place to facilitate a safer construction site as well as safer traffic movements for residents. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Residents will have access to their driveways throughout construction, please do not park on the road during work hours. 

 2023 - BUCHANAN CONCRETE STREET AND UTILITY RECONSTRUCTION

Public Informational Meeting January 25, 2023

To view the PowerPoint presentation click here.

To view Frequently Asked Questions click here.

Public Hearing February 8, 2023

To view the PowerPoint presentation click here.

To view Frequently Asked Questions click here.

2023 RECONSTRUCTION PROJECT – BUCHANAN STREET UTILITIES

Construction Project Timeline: March 20th to July 28th, 2023 

PROJECT – The Village of Little Chute’s 2023 Reconstruction is in the following location:

Buchanan Street; between East Main Street (STH “96”) and East North Avenue (CTH “OO”)

Contract No. 2023004

The construction project includes approximately 2,400 lineal feet of new sanitary sewer main, laterals, and associated precast concrete manholes. Project also includes approximately 1,740 lineal feet of water main, new water services, and miscellaneous fire hydrants, fittings, and water valves. Storm sewer includes approximately 2,000 lineal feet of pipe, as well as the associated storm laterals, manholes, and inlets. 

Kruczek Construction has been awarded the utility contract and is the General Contractor for this utility project. Crews have completed construction of the sanitary sewer mainline, sanitary laterals, water main, and water services. Kruczek is currently working on the installation of the new storm sewer main, crews continue working to the north on Buchanan Street.

Buchanan Street is an active construction site. For your safety as well as those working in the area, please avoid using this area when possible.

Traffic Impacts: The intersections of Buchanan Street and Main Street (STH 96) as well as East North Avenue (CTH “OO”) and Buchanan Street will remain open to local traffic only during normal construction activities. Intermittent lane restrictions and closures will take place to facilitate a safer construction site as well as safer traffic movements for residents. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Residents should expect additional restrictions due to installation of proposed utilities and should use alternate routes to limit traffic in the area when possible. . 

2023 - RANDOLPH CONCRETE STREET AND UTILITY RECONSTRUCTION

Public Hearing February 8, 2023

To view the PowerPoint presentation click here.

To view Frequently Asked Questions click here.

Contract No. 2023002

2023 RECONSTRUCTION PROJECT - RANDOLPH DRIVE UTILITIES

Project Completion Date: July 28th, 2023 

Project Location/Description:

The project is located on Randolph Drive and extends approximately 3,750 lineal feet. Project area begins at the intersection of E. Evergreen Drive and Randolph Drive, continues south on Randolph Drive for 900 feet, then east 2,150 feet, and north 700 feet, ending at the intersection of Randolph Drive and Hartzheim Drive.

The construction project includes approximately 4,495 lineal feet of 38”x 60” elliptical to 8-inch diameter storm sewer, 2,830 lineal feet of 8-inch diameter sanitary sewer main and 175 linear feet of 2-inch to 8-inch diameter sanitary sewer laterals, and 3,290 lineal feet of 12-inch to 6-inch diameter water main and 235 lineal feet of 1-1/4” to 2” water services.

Don Hietpas & Sons, Inc. has been awarded the contract and is the General Contractor for the utility portion of this project. Hietpas began installing storm sewer on the east end of the project at the intersection of Randolph Drive and Hartzheim Drive, construction continued south, then west on Randolph Drive. Crews will begin installation of the new water main on Monday, 6-5-23, at the intersection of Evergreen Drive and Randolph Drive, work will continue south on Randolph Drive. Please access Randolph Drive from the east from Buchanan Street and Hartzheim Drive.  

Randolph Drive is an active construction site. For your safety, as well as those working in the area, please use caution, and proceed slowly when utilizing Randolph Drive.

Traffic Impacts: The intersection of Evergreen Drive and Randolph Drive as well as the Hartzheim Drive/Buchanan Street/Randolph Drive intersection will remain open to local traffic only, during normal construction activities. Intermittent lane restrictions and closures will take place to facilitate a safer construction site as well as safer traffic movements. 

Heart of the Valley Metropolitan Sewerage District

The Heart of the Valley Metropolitan Sewerage District (HOVMSD), which serves the village of Little Chute, is moving ahead with plans for a major interceptor rehabilitation project. The project involves installation of a liner inside the pipe that carries sewage to the district’s treatment plant.

The project is needed after recent video inspections of the pipe found extensive surface corrosion, which threatens the longevity of the pipe. The project will allow the interceptor to serve its customers, and area residents and businesses, for decades to come.

Actual project work will begin in the spring of 2023. HOVMSD will provide periodic updates on the project to keep everyone informed of its progress. For more information go to https://hvmsd.org/.

Outagamie County Highway CC (Rosehill) Over I-41

I-41 southbound full closure for bridge repairs next week in Outagamie County

Crews to repair County Road CC over I-41
(Little Chute) The Wisconsin Department of Transportation (WisDOT) Northeast Region announces repair plans for the County Road CC/Rose Hill Road bridge over I-41 in the village of Little Chute, Outagamie County. An over-height vehicle struck the bridge on August 3, 2022 damaging a girder of the structure. Beginning Thursday, Sept. 1, 2022 crews will remove the damaged girder and install a concrete barrier along the location the girder was removed on County CC. This will re-establish two-way traffic with reduced shoulders on County CC. 
The bridge will remain with reduced shoulders and two-way traffic until it is removed as part of the upcoming I-41 Expansion Project. County CC/Rose Hill Road is currently open to a single lane of traffic with temporary traffic signals to direct motorists. Speed is reduced to 25 mph at the bridge.

New Concrete Sidewalk Information - Salt

With winter comes snow and ice removal. Besides shoveling or using a snowblower, many sidewalks, driveways, parking lots, and streets are covered in salt to melt ice and snow and make concrete safer. However, using salt on your new concrete could end up harming it.

If your home has a new concrete sidewalk this year due to TDS or AT&T construction do not place salt on it the first year.   


Your new concrete is in its most fragile state the first year after it is poured. It needs time to  cure. settle, and gain strength to avoid breaking or cracking in the future.